16:00:48 <gibi> #startmeeting nova
16:00:48 <opendevmeet> Meeting started Tue Aug  6 16:00:48 2024 UTC and is due to finish in 60 minutes.  The chair is gibi. Information about MeetBot at http://wiki.debian.org/MeetBot.
16:00:48 <opendevmeet> Useful Commands: #action #agreed #help #info #idea #link #topic #startvote.
16:00:48 <opendevmeet> The meeting name has been set to 'nova'
16:00:55 <elodilles> o/
16:01:03 <gibi> I will be your host today as bauzas is on PTO
16:01:10 <dansmith> o/
16:02:18 <gibi> #topic Bugs (stuck/critical)
16:02:20 <tkajinam> o/
16:02:25 <gibi> #info No Critical bug
16:02:39 <gibi> is there any bug that we need to discuss?
16:03:27 <gibi> #topic Gate status
16:03:33 <gibi> #link https://bugs.launchpad.net/nova/+bugs?field.tag=gate-failure Nova gate bugs
16:03:39 <gibi> #link https://etherpad.opendev.org/p/nova-ci-failures-minimal
16:03:46 <gibi> #link https://zuul.openstack.org/builds?project=openstack%2Fnova&project=openstack%2Fplacement&pipeline=periodic-weekly Nova&Placement periodic jobs status
16:04:14 <gibi> centos 9 based jobs are still read
16:04:16 <gibi> red
16:04:30 <gibi> due to
16:04:31 <gibi> Failed to enable unit: Unit file rabbitmq-server.service does not exist.
16:04:42 <dansmith> so some work was done in devstack recently,
16:05:07 <dansmith> related to the release repo, which I thought was going to fix some of it
16:05:12 <dansmith> rocky started working at least
16:05:40 <dansmith> but it was also (re-)asserted that stream is making it clear it's not stable enough for our purposes, which I definitely agree with :)
16:06:42 <dansmith> https://review.opendev.org/c/openstack/devstack/+/925368?tab=change-view-tab-header-zuul-results-summary
16:07:21 <gibi> thank dansmith for the pointers
16:08:02 <gibi> If somebody has the time to investigate further then go for it. :)
16:08:40 <gibi> but I guess as it is not blocking the CI directly it will take a while to get to it
16:09:21 <gibi> anything else about the centos jobs or about the gate in general?
16:10:06 <gibi> #topic Release Planning
16:10:20 <gibi> #link https://releases.openstack.org/dalmatian/schedule.html
16:10:31 <gibi> #info Dalmatian-3 in 3 weeks
16:10:44 <gibi> #topic Review priorities
16:10:49 <gibi> #link https://etherpad.opendev.org/p/nova-dalmatian-status
16:11:07 <gibi> Is there anything to discuss about the upcoming release?
16:12:07 <tkajinam> there is one open follow-up edit of the spec. would be nice if it can be quickly reviewed https://review.opendev.org/c/openstack/nova-specs/+/924563
16:12:36 <gibi> tkajinam: I will look at it after the meeting
16:12:48 <tkajinam> gibi, thx !
16:13:33 <gibi> #topic Stable Branches
16:13:42 <gibi> elodilles: hi! :)
16:13:45 <elodilles> o/
16:13:50 <elodilles> #info stable/202*.* gates seem to be OK
16:14:03 <elodilles> #info nova stable release patches (with CVE fix): https://review.opendev.org/q/project:openstack/releases+intopic:nova+is:open
16:14:18 <sean-k-mooney> dansmith: it may be worth condiering if the fibs jobs could move to rocky to be slightly more stable but ya i still agree in general. we can discusus that later if peopel want to do that work outside the meeting or in open dicussion at the end
16:14:22 <elodilles> waiting for release liaison reviews ^^^ o:)
16:14:37 <gibi> bauzas and Uggla are on PTO
16:14:48 <elodilles> gibi: ACK
16:14:57 <sean-k-mooney> amit is also a release liason
16:15:05 <dansmith> sean-k-mooney: yep
16:15:17 <elodilles> then auniyal is the only available release liaison o:)
16:15:19 <sean-k-mooney> auniyal: ^ can you prioitse that
16:15:48 <elodilles> thanks in advance o:)
16:15:56 <elodilles> #info stable branch status / gate failures tracking etherpad: https://etherpad.opendev.org/p/nova-stable-branch-ci
16:16:22 <elodilles> if anyone finds any gate issue then please add it there ^^^
16:16:35 <elodilles> that's all about stable from me
16:17:01 <gibi> elodilles: thanks!
16:17:08 <elodilles> np
16:17:16 <gibi> #topic vmwareapi 3rd-party CI efforts Highlights
16:17:20 <gibi> #info fwiesel on PTO until the 27th August.
16:17:33 <gibi> so I guess no news here
16:17:39 <gibi> #topic Open discussion
16:17:44 <gibi> (bauzas) Aug 6, 13 and 20 nova meetings
16:18:05 <gibi> so I took today's meeting but cannot do 13th or 20th
16:18:10 <gibi> any volunteer?
16:20:24 <gibi> then they are cancelled
16:20:47 <gibi> #info the meeting on the 13th and on the 20th are cancelled
16:21:00 <gibi> any other topic for today?
16:21:43 <dansmith> ++ for cancel :)
16:23:25 <gibi> I guess we are done for today then
16:23:31 <gibi> #endmeeting